Christmas Close Down

Christmas close down period.

In line with the building act, the statutory processing clock will be stopped over the Christmas period between 20 December 2020 and 11 January 2021. This period is excluded from the 20 working day period Councils are given to process applications.

Any consent application submitted on or after Friday 18 December will not begin to be processed until Monday 11 January.